Report No: 094061R-ITCEP07V06
Page: 107 of 123
Product Notebook
Test Item Conducted susceptibility
Test Mode Mode 2
Date of Test 2009/04/02 Test Site No.6 Shielded Room
Frequency
Range
(MHz)
Voltage
Applied
dBuV(V)
Inject
Method
Tested Port
of
EUT
Required
Criteria
Performance
Criteria
Complied To
Result
0.15~80 130 (3V) CDN AC IN A A PASS
0.15~80 130 (3V) CDN LAN A A PASS
0.15~80 130 (3V) CDN Telecom A A PASS
Note:
The testing performed is from lowest level up to the highest level as required by
standard, but only highest level is shown on the report.
Meet criteria A : Operate as intended during and after the test
Meet criteria B : Operate as intended after the test
Meet criteria C : Loss/Error of function
Additional Information
EUT stopped operation and could / could not be reset by operator at dBuV(V) at
frequency
MHz.
No false alarms or other malfunctions were observed during or after the test. The
acceptance criteria were met, and the EUT passed the test.